New Philadelphia road work advancing, 2025 paving list released

| April 22, 2025

Image source: freepik.com

NEW PHILADELPHIA (WJER) (April 22, 2025) – New Philadelphia has numerous projects in the streets around town in various stages of completion.

Service Director Ron McAbier was telling council that follow-up road work for the Franklin Square storm sewer project is winding down. Crews were restriping the pavement there last week.

He says the water line project at North Ave NE was wrapping up and the road will get paved either at the end of April or the first week of May.

And he says the renovation project for three of the quadrants at the downtown square is set to begin this July. Final designs are still being worked on.

The state announced last may it was awarding the city $2.9 million for the downtown quadrant project.

McAbier says the city is also planning about $1.7 million dollars in paving work this year, with nearly $1.2 million of that coming from the Ohio Department of Transportation.

2025 City of New Philadelphia Paving List:  

  • Providence Dr. SW & SE from Larkin Dr. SW to Goshen Ave. SE
  • College Ave. NW from 12th Street NW to Tuscarawas Ave. NW
  • Front Ave. SW from South Broadway to 4th Street SW
  • 1st Dr. NW from Park Ave. NW to Minnich Ave NW
  • Tuscora Ave. NW from North Broadway to 2nd St NW
  • Kelly St. NW from Wabash Ave. NW to Bowers Ave. NW
  • Bank Ln. SE from 4th St. SE to Tell St SE
  • Oak St. NW from Grandview Ave. NW to Carrie Ave NW
  • Fair Ave. NW from 2nd St. NW to 4th St. NW
  • Dale Ln. NW from North Broadway to 3rd St. NW • Rankin Court SW off 5th St. SW
  • 2nd St. from Front Ave. SE to Fair Ave. NW
  • Fair Ave. from 2nd St. NW to 2nd St. NE • Union Ave. from Ray Ave. NW to Martin St.
  • Reiser Ave. from 21st St. SE to Brightwood Rd.